How many seizings are required on each side of the cut for preformed rope according to ASME?

Study for the NEIEP Introduction to Elevators and Basic Electricity (200) Exam. Use engaging flashcards and multiple choice questions, each offering hints and explanations. Elevate your skills and excel in your exam!

Multiple Choice

How many seizings are required on each side of the cut for preformed rope according to ASME?

Explanation:
According to ASME guidelines, when using preformed rope, one seizing is required on each side of the cut. This practice ensures that the rope maintains its integrity and prevents fraying or unraveling at the cut points. Proper seizings help to stabilize the rope strands and allow for safe and effective operation within elevator systems. This requirement is particularly important in maintaining the safety and durability of the elevator's hoisting mechanism, as improper handling can lead to significant safety hazards and mechanical failures. Understanding this standard is crucial for anyone working with elevator systems to ensure compliance with safety protocols.

According to ASME guidelines, when using preformed rope, one seizing is required on each side of the cut. This practice ensures that the rope maintains its integrity and prevents fraying or unraveling at the cut points. Proper seizings help to stabilize the rope strands and allow for safe and effective operation within elevator systems. This requirement is particularly important in maintaining the safety and durability of the elevator's hoisting mechanism, as improper handling can lead to significant safety hazards and mechanical failures. Understanding this standard is crucial for anyone working with elevator systems to ensure compliance with safety protocols.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy